A document issued by the Office of the Municipal Engineer (OME)/Office of the Building Official (OBO), in accordance with the format outlined in NBCDO Memorandum Circular 01, series of 2020. This document advises owners/applicants to proceed with various construction activities such as construction, installation, addition, alteration, renovation, conversion, repair, moving, demolition, or other related work on a specific project/building/structure or portions thereof. Such activities are permitted once the accompanying principal plans, specifications, and other pertinent documents submitted with the application are deemed satisfactory and in substantial conformity with the National Building Code of the Philippines (NBCP) and its Implementing Rules and Regulations.
Step 1 of 4
APPLICATION FOR BUILDING PERMIT (ALL BUILDINGS / STRUCTURE OF MORE THAN TWO-STOREY, SPECIAL STRUCTURES UNDERGROUND STRUCTURES AND WINDOWLESS BUILDING)
External Services
Details
|
OFFICE/UNIT |
OFFICE OF THE MUNICIPAL ENGINEER |
|
CLASSIFICATION |
Highly Technical |
|
TYPE OF TRANSACTION |
G2C – Government to Citizens G2B – Government to Business G2G – Government to Government |
|
WHO MAY AVAIL |
Any person, firm or corporation including any government agencies or instrumentality who planned to erect, repair/renovate, convert any building or structure or cause the same to be done within the municipality. |
|
|
Construction / erection / addition / alteration / renovation / repair / legalization of the following Highly Technical Type of Project Activity / Structures:
All other transactions not expressly falling under either ‘Complex’ or ‘Highly Technical’ shall, for the purpose of these Guidelines, be considered as ‘Simple’ consistent with the mandate of RA No. 11032. |
Requirements
| # | Checklist Item | Where to Secure |
|---|---|---|
| 1 | ✓APPLICATION FORMS | ●Below |
| 2 | ✓Unified Application Form for Building Permit (4 original Copy, Signed and Sealed, and Notarized) | ●Owner/Applicant/Contractor. |
| 3 | ✓Architectural Permit application form (4 original Copy, Signed and Sealed) | ●Owner/Applicant/Contractor. |
| 4 | ✓Civil/Structural Permit application form (4 original Copy, Signed and Sealed) | ●Owner/Applicant/Contractor. |
| 5 | ✓Electrical Permit application form (4 original Copy, Signed and Sealed) | ●Owner/Applicant/Contractor. |
| 6 | ✓Mechanical Permit application form (4 original Copy, Signed and Sealed) (if applicable) | ●Owner/Applicant/Contractor. |
| 7 | ✓Sanitary Permit application form (4 original Copy, Signed and Sealed) (if applicable) | ●Owner/Applicant/Contractor. |
| 8 | ✓Plumbing Permit application form (4 original Copy, Signed and Sealed) (if applicable) | ●Owner/Applicant/Contractor. |
| 9 | ✓Electronics Permit application form (4 original Copy, Signed and Sealed) (if applicable) | ●Owner/Applicant/Contractor. |
| 10 | ✓TECHNICAL DOCUMENTS | ●Below |
| 11 | ✓Complete Plans with key plan, location map and vicinity map (4 sets, duly signed and sealed over the printed names of the duly licensed and registered corresponding professionals and by the owner/applicant) o. Architectural p. Civil/Structural q. Electrical r. Mechanical s. Sanitary t. Plumbing u. Electronics | ●Owner/Applicant/Contractor. |
| 12 | ✓Latest Verification Survey Plan and Survey Report. (1 original copy, signed and sealed by a Geodetic Engineer) | ●Owner/Applicant/Contractor. |
| 13 | ✓Bill of Materials (4 sets, signed and sealed by an Engineer/Architect) | ●Owner/Applicant/Contractor. |
| 14 | ✓Material Specification (4 sets, signed and sealed by an Engineer/Architect) | ●Owner/Applicant/Contractor. |
| 15 | ✓Structural Design and Analysis (3 sets, signed and sealed by a Civil/ Structural Engineer) (For 2-storey) | ●Owner/Applicant/Contractor. |
| 16 | ✓Boring and Plate Test and Seismic Load Analysis (3 sets, signed and sealed by a Civil / Structural Engineer) (For 2-storey with roof deck and up) | ●Owner/Applicant/Contractor. |
| 17 | ✓Latest PTR and Valid PRC ID and UAP / IAPOA (for Architect), Registered Civil Engineer/Structural Engineer, Professional Electrical Engineer, Registered Mechanical Engineer, Registered Sanitary Engineer, Registered Master Plumber, Registered Electronics Engineer (4 photocopy, originally signed and sealed) | ●Owner/Applicant/Contractor. |
| 18 | ✓Rainwater Collection System to be incorporated in Plumbing Plan (1 original copy) (if applicable) | ●Owner/Applicant/Contractor. |
| 19 | ✓Sewerage Treatment Plant (STP) Analysis (1 original copy, originally signed and sealed by Sanitary Engineer) (if applicable) | ●Owner/Applicant/Contractor. |
| 20 | ✓PROOF OF OWNERSHIP | ●Below |
| 21 | ✓Certified True Copy of Original or Transfer Certificate of Title (TCT/OCT), on file with the registry of Deeds (1 original copy) If in case the applicant is not the registered owner of the said lot / unit, in addition to TCT/OCT/Condominium Title, the following documents must be attached, whichever is applicable: i. Deed of Absolute Sale (1 original copy, Notarized) j. Deed of Donation (1 original copy, Notarized) k. Assignment of Rights (1 original copy, Notarized) l. Affidavit of Consent from Lot owner (1 original copy, Notarized) v. Extra Judicial Settlement (1 original copy, Notarized) (if registered owner is deceased). vi. Special Power of Attorney (1 original copy, Notarized) | ●Owner/Applicant/Contractor. |
| 22 | ✓Tax Declaration (1 original copy) | ●Owner/Applicant/Contractor. |
| 23 | ✓Tax Clearance (1 original copy) | ●Owner/Applicant/Contractor. |
| 24 | ✓CLEARANCE / CERTIFICATION | ●Below |
| 25 | ✓Community Tax Certificate (1 photocopy) | ●Municipal Treasury Office |
| 26 | ✓Updated tax receipt (1 photocopy) | ●Municipal Treasury Office |
| 27 | ✓Certificate of No Improvement or with Improvement (1 original copy) | ●Municipal Assessor Office |
| 28 | ✓Locational Clearance (3 original copy, Notarized) | ●Municipal Planning and Development Office |
| 29 | ✓Evaluation Report (3 original copy) | ●Municipal Planning and Development Office |
| 30 | ✓Decision of Zoning (3 original copy) | ●Municipal Planning and Development Office |
| 31 | ✓Three (3) original copy of Declaration Form (notarized) | ●Municipal Engineering Office |
| 32 | ✓Fire Safety Evaluation Clearance (OBO copy) | ●Municipal Fire Station |
| 33 | ✓Barangay Permit to Construct (1 original copy) | ●From barangay where the building/structure will be constructed. |
| 34 | ✓Authorization Letter with attached photocopy of ID of Owner/applicant and representative (1 original copy) (if applicable) | ●Owner/Applicant/Contractor. |
| 35 | ✓DOH Clearance (if applicable) | ●Department of Health Office |
| 36 | ✓PHIVOLCS Clearance (if applicable) | ●Philippine Institute of Volcanology and Seismology Office |
| 37 | ✓DPWH Clearance - for road-right-of-way clearance for national and provincial road (1 original copy) (if applicable) | ●Department of Public Works and Highways Office |
| 38 | ✓NIA Clearance - for easement of all bodies of water (1 original copy) (if applicable) | ●National Irrigation Administration Office |
| 39 | ✓MENRO Clearance (1 original copy) (if applicable) | ●Municipal Environment and Natural Resources Office |
| 40 | ✓Environmental Compliance Certificate from DENR (1 original copy) (if applicable) (if applicable) | ●Department of Environment and Natural Resources Office |
| 41 | ✓CAAP Clearance – for cell site tower (1 original copy) (if applicable) | ●Civil Aviation Authority of the Philippines Office |
5 STEPS
|
CLIENT STEPS |
AGENCY ACTION |
FEES TO BE PAID |
PROCESSING TIME |
PERSON RESPONSIBLE |
|
1.1 Receive and verify the completeness of application documents in accordance with the provided checklist of requirements. (If complete, issue acknowledgement receipt)
1.2 Encode received application and documents.
1.3 Site Inspection, check condition of the lot and its boundaries, check adopted setback, check status of construction. And prepare inspection report.
1.4 Evaluation of building plans and other supporting documents. Land Use and Zoning, Line and Grade, Architectural, Structural, Electrical, Mechanical, Sanitary, Plumbing, and Electronics
1.5 Prepare order of payment
1.6 Sign and approve order of payment. |
None
None
None
None
None
None
|
2 hours
1 hour
1 day
17 days
4 hours
1 hour |
Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Ralph Jayson A. Loto
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Engineering Office |
|
2. Issue approved order of payment |
None
|
5 minutes |
Engr. Ralph Jayson A. Loto Engineering Office |
|
3. Received payment and issue Official Receipt (O.R.) |
Refer to NBCP (PD1096) prescribed Schedule of Fees |
20 minutes |
Cashier Municipal Treasurer’s Office |
|
4.1 Check / Record O.R. Number, and assign Bldg. Permit Number, Architectural Permit Number, Civil/Structural Permit Number, Electrical Permit Number, Mechanical Permit Number, Sanitary Permit Number Plumbing Permit Number, Electronics Permit Number, Encode on permit forms, stamp plans and permits, and Segregation of plans and documents for applicant and office copy.
4.2 Signed and approved the Building and Ancillary plans and Permit |
None
None
|
4 hours
3 hours
|
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Regino John S. Salamanca Engineering Office
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Engineering Office |
|
5. Release approved Building and Ancillary plans and permit and checklist to owner or applicant. |
None
|
35 minutes |
Engr. Marlyn L. Laureta Engr. Ralph Jayson A. Loto Engineering Office |
|
|
TOTAL |
Refer to NBCP (PD1096) prescribed Schedule of Fees |
20 DAYS |
|